Why MRL is the export default

Removing the machine room reduces building cost, simplifies the architectural interface and cuts on-site installation work. For export projects it also reduces the number of separate crates and the amount of wiring the local installer has to terminate. The trade-off is that the shaft must accommodate the machine, the controller cabinet and the required access clearances — so the GA drawing has to be approved early.

Indicative planning parameters

Indicative MRL passenger lift planning parameters
ParameterIndicative rangeNote
Rated load630–1250 kgSelected from building traffic and car size
Speed1.0 / 1.5 / 1.75 m/sDrive and controller sized to travel height
Stops6–16 and aboveLanding door and controller I/O schedule
Machine positionTop of shaft or side of shaftDriven by overhead height and structural layout
Control cabinetIntegrated near the top landing / shaftAccess and ventilation must be designed in
Supply3-phase 380 / 415 V 50 Hz or 480 V 60 HzConfirmed before production, see voltage guide

Planning ranges only. Final load, speed and dimensions are fixed in the approved GA drawing and technical agreement.

Electrical configuration is the main export risk

A motor wound for 480 V / 60 Hz behaves differently on a 380 V / 50 Hz network: synchronous speed falls with frequency, cooling fan output changes and the VVVF drive parameters no longer match. For a 16-stop MRL project, a 15 kW and an 18.5 kW machine also imply different cable sizes, protective devices and starting currents. These are engineering decisions made at the quotation stage, not corrections made on site.

Read the power supply & voltage adaptation guide, which covers 480 V → 380 V conversion, 415 V / 50 Hz Gulf standards and motor power selection.

Documentation and handover

Every MRL unit ships with a GA drawing, electrical schematic, terminal wiring diagram, load and function test record, parts list, installation/operation/maintenance manuals and a crate-marked packing list. That file is what a local installation team uses to commission the lift, and it is what a buyer should audit before signing.